Deere Northpark Expansion
Project Owner
Deere
Designer
Walter Robbs, a Michael Graves Company
Location
Kernersville
Description
With a timetable of less than one year from start of design to completion, work had to begin during the winter, requiring thorough preplanning to reduce any time lost from freezing temperatures and wet weather. By installing the stone base under the building slab prior to the excavation for foundations, Blum ensured that work could continue despite the weather. Building Information Modeling (BIM) technology was used to locate and map existing sub-surface utilities so that the relocation of the lines could be coordinated with utility companies while work continued. The expansion was completed successfully and on schedule.